Kimberly Clark LFGTE Project


Previous Photo | Next Photo
Project Objective:
Design, install and commission seamless transfer boiler fuel conversion system for the plant's 130,000 #/hr package boiler.  Design will allow for either stand-alone firing or co-firing of the two options for fuel (natural gas or LFG). 
 
Project Statistics:
  • The LFG section designed to fire 100% of the Landfill's future production of 3,500 SCFM
  • Boiler Controls and BMS was upgraded to Allen Bradley Control Logics Platform for conformity with plant's #2 boiler
  • Based on DOE's Average US household energy usuage of 36.3 MMBtu/yr (10,660 kw-hr/yr), this project presently, offsets the equivalent energy needed to power 7,500 homes for one year