Project Objective:
Design, install and commission seamless transfer boiler fuel conversion system for the plant's 130,000 #/hr package boiler. Design will allow for either stand-alone firing or co-firing of the two options for fuel (natural gas or LFG).
Project Statistics:
-
The LFG section designed to fire 100% of the Landfill's future production of 3,500 SCFM
-
Boiler Controls and BMS was upgraded to Allen Bradley Control Logics Platform for conformity with plant's #2 boiler
-
Based on DOE's Average US household energy usuage of 36.3 MMBtu/yr (10,660 kw-hr/yr), this project presently, offsets the equivalent energy needed to power 7,500 homes for one year
|